The lift of the MCHE, which weighed a total of 650,000 lbs. (295 tonnes), was a dual lift utilizing a Terex-Demag CC-2800 crawler crane as the main crane and a Liebherr LR-1300sx crawler crane on the tail. The inclement weather was a source of many challenges including broadening the travel path for transport, smoothing the roads, and re-doing the crane pads and travel path after storms had moved through.

MAMMOET HAS COMPLETED A MAJOR MILESTONE WITH THE INSTALLATION OF THE MAIN CRYOGENIC HEAT EXCHANGER (MCHE), CONSIDERED TO BE THE HEART OF TRAIN ONE, AT A LIQUEFACTION PROJECT ALONG THE U.S. GULF COAST.

The project is currently comprised of three natural gas liquefaction trains with approved liquefied natural gas (LNG) export capacity of 1.7 billion cubic feet per day. When complete, it will be one of the largest LNG export terminals in the US.

“The combined efforts and hard work of all crews on site made this a safe and successful installation. The crews displayed an ‘adapt and overcome’ mentality to many obstacles to execute this operation in a truly professional fashion.”

Randall Fox, Mammoet USA Senior Project Manager

mammoet-liebherr-crawler-machine.market-1


Discover CraneMarket's great selection of cranes, crane equipment & parts.
e.g. Down Cab Cranes for Sale and Rent

Continue to our shop section to browse all cranes for sale
e.g. Crawler Cranes for Sale and Rent

Let's finish your next project together! Find out how we can help you.
e.g. Lattice Boom Cranes for Sale and Rent